West Shore Park
The Colony, Texas
MHS worked with the City of The Colony to design and develop a neighborhood park within the Eastvale neighboorhood. Adjacent to Lewisville Lake the park had considerable grade change and handled stormwater drainage from the surrounding neighborhood. These factors posed the most difficult to design with during the park development.
Comprised of two terraced playgrounds, one for 2-5 and the other for 5-12 year olds, berm play, terraced stone steps, a covered picnic area, and native plantings West Shore Park is a great park for use by all of the surrounding area.
Project Size:
Area of Development: +/- 1.25 Acres
Design Time:
+/- 6 Months
Construction Duration:
Start: January 2023
Final Completion: March 2024
Initial Construction Amount:
$656,822.26
Final Cost:
$629,641.78
Services Provided:
Discovery and Programming
Schematic Design
Design Development
Construction Documentation
Cost Estimation
Bidding and Contractor Selection
Construction Administration